Our first milestone was to make Technical and Financial report. As a team we had to pull off the draft report including organizational chart, methods and techniques, aim, scopes, goals and objectives, milestones, a working plan and gantt chart, and other relevant information.
​
This report was very essential to be planned wisely as based on this we had to proceed. All the details are mentioned here to know our progress while building this report.
OCTOBER 22, 2021
​
-
Selection of project manager and group members
-
Formation of company name: Morpheus Consultant Inc.
-
Formation of company organization
-
Discussion and explanation of team members’ responsibilities
-
Discussion of TOR Project
-
Discussion of proposed technical and financial report
-
Task distribution for proposed technical and financial report
OCTOBER 23-26, 2021
-
The development of the first draft of proposed technical and financial report


OCTOBER 29, 2021
-
Additional member was added (Brendan)
-
The first CRIT session for the proposed technical and financial draft report
-
Dr Zak's comments:
-
The misinterpretation of the project (because we wrote about how we will construct the low carbon city, not about the blueprint) so we must change it back to low carbon city blueprint
-
The organization color identity (needs to be fixed)
-
The background image needs to be transparent
-
After the CRIT, we review back all the comments and discussed on how to solve and fix it based on the given TOR project.
-
For Brendan only – was given task and responsibilities in the group

NOVEMBER 1 - 4, 2021
-
The development of second draft of proposed technical and financial report
-
Followed all the comments made by Dr Zak
-
Repaired the report based on the TOR project
-
Create the report in one Word document, not in PowerPoint slides
NOVEMBER 5, 2021
-
Submission of the second draft of the proposed technical and financial report
NOVEMBER 12, 2021
-
The second CRIT session for the submitted proposed technical and financial report
-
Dr Zakiah's comments:
-
The cover page is too formal and not showing the company identity because we should not do a cover page like other usual assignment – so need to fix it
-
The table of content is too old school
-
Too advance as some of the sections supposedly belongs to Inception report – summarize and delete few parts that should not be included in Proposed Technical and Financial Report
-
No site area
-
Must ensure all team member image in organizational chart is in line and align to each other
-
Own a good component of contents and understand what needs to be put in low carbon city blueprint
-
The project planning must repair as it brings confusion



NOVEMBER 14 - DECEMBER 2, 2021
-
14/11/2021: Group discussion to modify and improve second draft of the proposed technical and financial report


-
15/11/2021 – 1/12/2021: Development of final proposed technical and financial report


​​
-
2/12/2021: Checking the full final report with group members


DECEMBER 3, 2021
-
Submission of final proposed technical and financial report